Home CPCSD

Administration Fire Department Parks Recreation Department CC&R and Architectural Review Office

Cameron Park Community Center

We will keep you abreast of our progress at our monthly Board meetings and on this website. If you have additional questions, please telephone the District Office at (530) 677-2231.

AS OF 04/23/2008 Regularly Scheduled Board Meeting:

At the Special Board Meeting 11/29/2007:
.........Director Coze clarified that, according to the bond counsel, the monies from the bond can be used to construct and equip not acquire, construct, and equip. This was mentioned due to the possibility that had been brought up from the previous meeting that the monies be used to purchase or lease the ACE Hardware building instead of building Option 1.

.........Brian Brown, WLC Architects, gave a brief update from the last meeting. The November 14, 2007 meeting ended with a request to look into a redesign to allow for more than one of the amenities that the voters wanted. After researching the time and costs of a redesign, it was shown that, depending on the scope of the redesign, only a 2500 square foot building would be all that the District could end up with, at best.

........Public comment continued and the following was contributed: the Board was implored to seek out partnerships with established amenities to provide the needed services. One member felt that all or nothing should be built. More than half of those who spoke reminded the Board to keep the District’s financial situation (before and after construction) in mind. And the option of buying the old ACE Hardware building was revisited more than once to no avail; the available funds are too restrictive to allow it.

Action: To move forward with Option 1 (Assembly Hall, Stage, Kitchen, Offices, Meeting/Classroom, Senior Center, and Teen Room); proceed with an alternate bid package to include Option 3A (Option 1 as well as the pool and pool support facilities) to be determined once the bids are received. Vote 5-0


At the Regular Board Meeting 04/23/2008:
.......... Director Johnson provided background information pertaining to the alternate bid for the Community Center. This item was tabled from last month’s meeting because there were three bids that needed to be re-bid, including the pool. This allowed other contractors the availability to bid. Meanwhile, staff had created a mock community pool complete with a program schedule, list of fees, and finally the costs associated with those programs. This was presented in the Board packets. The mock pool was unable to cover its costs.

President Johnson read a letter submitted by a Cameron Park resident, as the individual could not be in attendance to speak. The letter reflected disappointment in the deficit a swimming pool would impose on the District from operating costs. Director Johnson continued with discussion with a list of bidders that was made available to the Board at 5 pm the day of the meeting. As this list was different than the one provided in the Board packet, Directors Johnson and Clarke had some clarification questions. Kirk McKillop, ProWest Constructors, stated that he was prepared to share the progress of construction and the savings that the CSD has from the lower-than-estimated bids that recently came in. Any questions about the Preconstruction costs (i.e. the contingency) would have to be answered by the Preconstruction President, Mike Quinn. McKillop had a call into Dan Polen and Mike Quinn, Preconstruction for ProWest.

Director Gerger stated that the operating costs of the pool, as shown in a negative value, should be enough to determine if the pool should be built. It could be a waste of time to prolong the discussion because while we may have enough money to actually build the pool, more importantly, we may not have enough money to have it. Director Johnson answered that his questions are relevant and, in response to the deficit pools run each season, he has had discussions with residents regarding handling the deficit. Any vote would be ridiculous with insufficient information.

This item was tabled to a Special Board Meeting, date to be determined upon e-mails to Directors and Dan Polen, where discussion can take place once the answers to some questions are available.
Action: Tabled to a Special Board Meeting, date TBD


Newsletters Provided by ProWest Constructors as to the progress of construction:

April 2008
June 2008

 

 

Home | Administration | Fire Department | Parks | CC&R / ARC | Recreation Dept.

Comments, Questions, Concerns? Email CPCSD
Page Last updated: Tuesday, June 17, 2008 4:47 PM